Public Works Minister Inspects Progress on Annaba Phosphate Port Expansion

Minister of Public Works and Basic Infrastructure Abdelkader Djellaoui made a field visit to Annaba province to review progress on the Annaba phosphate port expansion project, which includes building the mining quay as part of the integrated phosphate project, in a bid to strengthen the port's capacity and support…

img-01

Minister of Public Works and Basic Infrastructure Abdelkader Djellaoui made a field visit to Annaba province to review progress on the Annaba phosphate port expansion project, which includes building the mining quay as part of the integrated phosphate project, in a bid to strengthen the port's capacity and support phosphate extraction and transport.
The minister inspected the project's various worksites and facilities, along with the material and human resources deployed, noting that infrastructure work on the mining quay has reached an advanced stage. The works include building a 1,600-meter quay and an 82-hectare back platform.
To date, 1,180 piles have been driven out of 1,322 planned, at a rate of 7 to 10 piles per day. Work also continues on the quay wall's superstructure, with 107 reinforced concrete beams installed and 880 precast reinforced concrete slabs completed, while preparations are under way to pour the top slab that forms the quay's upper structure.
Aboard the Chinese vessel Tongjun, assigned specifically to the project, the minister reviewed dredging and reclamation works aimed at reaching a depth of 16 meters below sea level in the basin. The vessel has an operating capacity of 35,000 cubic meters per day and is equipped with modern technologies being used in Algeria for the first time, which are expected to boost productivity and shorten completion times.
The minister also listened to a technical presentation on the vessel's smart monitoring and management system, which allows precise, automated control of dredging, pumping and reclamation operations and real-time tracking, using navigation, communication and positioning technologies. The presentation also covered its dual-fuel system (methanol and diesel), which improves energy efficiency and reduces environmental impact, as well as its ability to operate in difficult marine and weather conditions and to dredge at depths ranging from 6 to 120 meters. The volume of material dredged has reached 11 million cubic meters out of 13 million planned.
As for backfilling with marine sand, about 2.3 million cubic meters have been completed on the quay's rear platform, while the total backfill volume completed has exceeded 3.4 million cubic meters. Vibroflotation of the sandy soil also continues to improve its properties and load-bearing capacity, alongside the use of prefabricated vertical drains (PVD) to control soil settlement.
Regarding the extension of the old breakwater, about 4.32 million tons of stone have been placed out of 5.5 million tons planned, along with heavy rocks and concrete blocks to provide protection against waves and sea currents.
At the close of the visit, the minister expressed satisfaction with the progress of the works and the pace of delivery, particularly after the site was reinforced with a second specialized vessel for pile driving and securing marine works, which raised productivity and accelerated progress. He praised the resources deployed and stressed the need to maintain mobilization and strengthen coordination among all stakeholders to complete the works and deliver the project on schedule.