The Sonelgaz Group announced the launch of a large-scale national operation to maintain and strengthen electrical facilities. This initiative aims to support and enhance the readiness of the isolated electrical grid in the Great South, ensuring the continuity and quality of service.
The group explained in a statement that this operation involves technical teams specializing in electricity operations from the distribution directorates of Skikda, Setif, Souk Ahras, Tebessa, Oum El Bouaghi, Mila, Annaba, Bejaia, and Batna, starting from the Setif distribution directorate.
To ensure the success of this first-of-its-kind operation, nine technical teams have been deployed, each consisting of 10 members. A total of 27 vehicles have been provided, including 18 four-wheel-drive vehicles and nine light trucks. These teams include various specialties, such as electricians, technicians, and work agents, in addition to district heads and team leaders.
The operation is scheduled to last for 15 days, with work beginning on Sunday, January 11, 2026. It will cover various network maintenance tasks, particularly medium and low-voltage networks, 30 kV lines, electrical transformers, and all electrical facilities belonging to the distribution network.
These works will be carried out across the provinces of Ouargla (El Borma border district), El Menia, Djanet, Illizi, Tamanrasset, and In Guezzam. The goal is to secure the networks and ensure the continuity and quality of energy services, confirming Sonelgaz’s commitment to mobilizing all its human and material resources to ensure a comfortable and stable summer for its customers, while continuing its leading role in serving citizens and supporting the national economy.